1.866.552.5246
By Eric G. Amhaus and Brian Erickson, M.S., Professional Investigative Engineers
The air barrier is an important component of a building
enclosure system that can improve HVAC system performance,
increase occupant comfort, improve smoke/fire control,
decrease damage to enclosure components from condensation,
and maybe most importantly reduce energy consumption. The
air barrier is defined by the Air Barrier Association of America
(ABAA) [1] as an assembly to "control the unintended movement
of air into and out of a building enclosure." By reducing the air
infiltration and exfiltration through the exterior enclosure to
almost negligible amounts, the air barrier reduces energy
consumption by reducing the associated heating and cooling
loads and allows the designers to downsize the HVAC system.
The reduction in uncontrolled air movement through a building
enclosure will also minimize the potential for interstitial
condensation development within the envelope cavity by
reducing the water vapor carried by airflow and its contact with
surfaces below the dew point temperature. In heating climates,
the focus is on interior moisture-laden air exfiltration, whereas
in humid, cooling climates, the concern is reversed and focuses
on exterior moisture-laden air infiltration into air-conditioned
structures. Air barriers also improve occupant comfort through
noise transmission reduction, along with odor and contaminant
control.
The building design and construction industry has recently
become more aware of the benefits of air barriers and begun to
implement them on new and rehabilitation construction
projects. This awareness has even translated into mandates and
requirements for air barriers by some state and federal
governing agencies above and beyond the somewhat general
and non-quantitative air tightness requirements of the
International Energy Code (IEC) or ASHRAE Standard 90.1.
States such as Massachusetts, Wisconsin, Michigan and
Minnesota have incorporated air barrier requirements into their
state building codes, but have not implemented quantitative air
tightness requirements that are verified by testing. The absence
of quantitative testing lends skepticism to any impact the
requirements of the IEC, ASHRAE 90.1, and local jurisdictions
actually have on the air-tightness of buildings. In contrast,
countries such as
Ireland and the United
Kingdom have included
the incorporation,
inspection and testing
of air barrier systems as
a requirement within
their building codes for
many years.
"...the air barrier reduces energy
consumption by reducing the
associated heating and cooling
loads and allows the designers
to downsize the HVAC system."
When qualitative or quantitative air barrier requirements are
implemented on a new or rehabilitation construction project,
the air barrier consultant or testing agency is a sub-consulting
profession that will join the ranks of the design and/or
construction team. An engineer, architect, or consulting firm
that is well versed in exterior enclosure systems (water,
thermal, air and vapor) may be able to provide a single source
for an enclosure commissioning program [2] that includes predesign
objectives, schematic and design development
consultation, design and documentation review, site observation
quality assurance, and performance testing services that now
incorporates the air barrier.
While a number of articles have been published on air barriers
and exterior enclosure commissioning [3, 4, 5, and 6 to name a
few], the focus of this article is on the considerations for an air
barrier performance testing program that should be
implemented if the benefits of the air barrier are to be fully
realized by the building end user.
While this list is not all-inclusive and could be added to or amended, it is a basis for the industry to consider and discusses ten important factors when implementing an air barrier performance testing and diagnostic evaluation program.
The testing firm should possess applicable experience accomplishing air barrier performance testing by fan pressurization methods (ASTM E779-03 [7] and E1827-02 [8]) on large-scale projects, not simply residential "blower door" testing. The testing equipment and level of building systems knowledge required on large scale projects, generally considered to be over 10,000 square feet, is far greater compared to single-family homes for obvious reasons. The testing firm should submit projects of similar size and scope prior to being retained.
An understanding of the complexities involved in testing various building sizes, shapes, and types is necessary for the end results to be a valid and accurate representation of the air tightness metric of the building enclosure. For example, there is a difference between accomplishing air barrier testing on a singlestory pre-cast concrete structure with a slab on grade floor and packaged roof-top HVAC units, as compared to testing a multistory wood framed structure with long corridors, elevator shafts, stairwells, sub-floor crawlspace, and a water-loop heatpump HVAC system with heat-recovery ventilators; the latter requires a more diligent preparation protocol and contains many additional variables that will affect the end result of the test, possibly indicating a "tighter" or "looser" building enclosure than in actuality. It may not be feasible to test the building as a "single zone" and thus sections, wings, or floors in the building need to be isolated or compartmentalized and results extrapolated. If these variables are not clearly defined within the project specifications, then the consultant or testing agency should be knowledgeable enough to know which questions to ask or provide recommendations and guidance to the owner/design-construction team well in advance of the actual testing.
Extensive knowledge, background and experience in all facets of building envelope enclosure systems is necessary so the air barrier system does not unintentionally adversely affect other enclosure requirements such as water vapor transmission. This includes all types of roofing (steep slope and low slope), exterior wall types (mass reservoir, barrier, water managed, rain screen), cladding or façade types and materials, fenestrations (doors and windows), curtain walls, flashing mechanisms, sealants, expansion joints, insulation, and all other component parts and systems forming the exterior floor, wall, or roof assemblies. A building enclosure consulting firm or architectural/engineering firm that can also accomplish building performance testing would be preferred over a company that just provides testing services. The former would minimize the potential for corrective measures to remedy air leakage, such as sealing an exterior joint or transition that may adversely affect the performance of other building systems. For example, if the joint or transition is a drainage or weep mechanism for the façade's water management system, it could result in serious concerns with the façade's inability to properly direct water out and away from the structure if inadvertently sealed for air tightness.
An understanding of the building's HVAC components and systems is vital so they can be taken into consideration and properly prepared prior to any performance testing, specifically the ventilation and air distribution systems. Should such systems be included in the test (as-is), should they be isolated from the test, or are they relevant (all components within the building enclosure)? The HVAC system preparation parameters may not be incorporated in the air barrier testing specifications as commonly referenced test standards allow for flexibility. Isolation of air-distribution systems and "intentional" holes in the enclosure will provide a more accurate air-tightness measurement of the building enclosure, but at the expense of significant time and effort to seal all those openings in the enclosure or within the building. The testing agency's knowledge of mechanical system air distribution networks could also allow expedient preparation if only certain components of the HVAC air distribution system require isolation. For example, it would save time if only the outdoor air intake on RTUs were sealed rather than every supply and return register within the test zone. Exhaust fan registers may not need to be isolated if only a depressurization test is required by the project documents as the (non-motorized) damper should close during the test, effectively isolating it from the enclosure.
Building preparation
generally includes
accurate building takeoffs
to determine fan
capacity requirements,
isolation of HVAC
components and
temporary system
disabling, plumbing
traps filled, fenestrations locked, and many additional tasks that
may or may not be outlined in the project specifications or
testing protocols. Frequently, air barrier project requirements
or testing protocols are absent of such specific tasks, thus
buildings are prepared differently and the results are not
repeatable and cannot be compared between different
buildings. The testing program must clearly identify all
preparatory tasks to achieve repeatable and comparable tests in
addition to eliminating conflicting preparatory opinions by onsite
witnesses, immediately prior to testing.
"An understanding of the building's
HVAC components and systems is
vital so they can be taken into
consideration and properly prepared
prior to any performance testing,
specifically the ventilation and air
distribution systems. "
If the air barrier test program specifies on-site pressurization
(not an off-site mock-up), the specifications should include a
requirement for adequately sized, rated, and calibrated
equipment with up-to-date calibration records. Of course, the
larger the building, the more cubic feet per minute (cfm) of air
that will be required from the fan(s) to pressurize or
depressurize the structure to the target value, say 50-75
Pascals. Adequate fan capacity should be calculated prior to
arriving on-site based on the air tightness requirements that are
normalized by some building metric, such as envelope area or
volume. For example, if the air tightness requirement is 0.25
cfm/ft2envelope @ 75-Pa, envelope takeoffs can be accomplished
and multiplied by 0.25 to determine the capacity required if the
building is to achieve its target pressure differential.
Utilizing a building's HVAC supply air fans may be necessary for
large buildings where traditional portable fans may not be
practical. The use of the HVAC system for air-tightness testing
involves a variety of additional considerations including accurate
supply air flow measurement techniques, proper damper
positioning, and, of course, the cooperation from the
mechanical designer-of-record and facility manager. The report
by Bahnfleth [9] provides for many considerations in large
building air-tightness testing using the HVAC system.
The party administering the tests should have the equipment
capability that allows for flexibility in the testing regimen due to
differing building geometries and sizes, and possible sectional
isolation and extrapolation. Pressure equalization must be
achieved at all points within a building within 10%, or 2.5Pa,
depending on the test protocol and professional judgment of the testing parties. Utilization of long pressure taps, sometimes
in excess of 200-feet, both inside and outside, are necessary to
verify that a uniform pressure differential is achieved within the
test zone, especially when windy conditions exist (in excess of
10-mph). The exterior pressure taps can be connected to a
manifold to average the exterior pressure readings if localized
wind-induced pressures will affect the baseline building
pressures and subsequent pressure readings in the judgment of
the testing agency. Pressure loss within the taps/tubing is not
generally considered, assuming the tubing is free of small pin
holes, kinks or rain water.
In some cases a single high-capacity fan (trailer mounted),
three-fan or even a six-fan assembly in one centralized location
will provide the adequate capacity to achieve the desired
pressure differential at all points within the structure. This
generally applies to buildings with open floor plans such as
warehouses or some open office spaces. On the other hand,
complex building geometries will require multiple fan assemblies
located in strategic locations within the building and operated
simultaneously to achieve the desired pressure differential at all
points monitored within the building. If the testing entity is not
prepared with equipment flexible enough to make such
adaptations, it will result in a non-uniform pressure differential
distribution within the building and thus questionable test
results.
In addition, the flexibility of testing equipment becomes more
valuable if more specific tests are warranted while on-site. For
example, measuring air leakage through fenestrations may be
necessary (ASTM E783-93 [10]) to segregate and determine
specific building air leakage rates at specific components of the
structure if it is suspected they are large contributing sources to
the overall building leakage.
Diagnostic evaluation of the air barrier performance (ASTM E1186-03 [13]) should be included in any air barrier performance testing program. These diagnostics are most commonly accomplished utilizing infrared thermography and/or smoke tracer and generation devices. The program should employ certified and experienced infrared thermographers that are able to accurately diagnose specific areas of air leakage for targeted retroactive air sealing. Infrared cameras have become relatively inexpensive to purchase over the last decade so many companies now possess an infrared camera; however, the knowledge of operation and accurate diagnoses may be suspect. Even certified infrared thermographers may not have the experience necessary with building systems to render effective evaluation during diagnostic testing of a building's air barrier. For example, is the infrared image confirming air loss or is it potentially an infrared reflection from an adjacent substrate or material, solar loading, or radiation? A mis-diagnosis of air leakage could result in wasted resources in retroactive air tightening and as described in #3, could adversely affect theperformance of the building enclosure. Infrared cameras should be capable of achieving the required resolution, and should also have updated calibration with records. Lastly, air temperature differentials are required between the interior and exterior during diagnostic testing for effective infrared imaging and air leakage detection. Hence, the time of day for the diagnostic testing and manipulation of the building's heating or cooling systems may need to be considered. Baseline infrared imaging should always be accomplished before pressurization and diagnostic testing is accomplished with the infrared camera. Infrared and digital images captured should be documented on building elevation, floor and roof plans should a review of their location on the building be desired at a later date.
The air barrier system may be tested in a mock-up scenario (ASTM E2357-05 [14]), on or off-site, prior to commencement of construction. Some buildings are too large and complex to reasonably achieve a uniform pressure differential across the entire building envelope by the testing equipment available today. Use of the building's HVAC system to achieve pressure differentials, while possible, introduces uncertainty and requires exceptional knowledge of building control systems by the testing agency or mechanical designer of record. In these circumstances, it is generally beneficial to construct an off-site mock up of a typical wall assembly that includes most or all of the relevant components so the standards of construction can be established and challenging interfaces are not simply "worked out", untested, in the field. The testing of mock-up wall assemblies should not necessarily be limited to only large buildings, but should be considered for smaller or complex buildings as well. If mock-ups are utilized, testing can be performed not only on the air barrier system, but also the thermal barrier, water penetration barrier, structural dynamics, and other metrics as required by the Owner or project specifications. Certainly discovering that an air barrier system does not meet the required design performance criteria after completion of the building could be a costly lesson, further increasing the benefit of mock-up or intermittent performance tests whether on or offsite. It has been estimated that the cost to repair a failed air barrier could be greater than 50 times the cost of installing it correctly the first time [15]."Diagnostic evaluation of the air barrier performance (ASTM E1186-03 [13]) should be included in any air barrier performance testing program."
Consideration should be given to the potential for bias if the testing agency is the same as the air barrier designer and the quality assurance or oversight entity. In a perfect world, the test results should be uniform and repeatable, or at least within 10%, between any qualified testing agency and any calibrated equipment. However, if the air barrier system fails to meet the project requirement, the costs of repair and re-testing will be borne by some entity. If that entity is also the one performing the testing, the possibility of bias is real and should be acknowledged.
Without a quantifiable air barrier performance testing
requirement, the actual benefits of an air barrier system may
not be realized by the building end user. Efforts are continual
to incorporate such quantitative requirements into the IEC,
ASHRAE 90.1, and local jurisdictions but to date only a limited
number of entities are requiring performance testing of the air
barrier system.
The considerations within this paper should assist in avoiding
mistakes and non-repeatable data that may result in costly
expenditures after the fact. Using the old adage "a chain is only
as strong as its weakest link," if the considerations above are
not implemented into the decision-making process for the
testing program, accurate diagnostic evaluations and repeatable
performance results for the air barrier assembly may not be
achieved and the overall goal of an air-tight building may be
compromised.
Eric Amhaus and Brian Erickson have years of experience in large
building performance testing and diagnostic evaluations with the
quality assurance consulting department of Professional
Investigative Engineers (PIE). They have consulted with governing
agencies on the development and implementation of air barrier
testing programs. PIE is a multi-faceted forensic engineering firm
with departments servicing forensic investigations in the insurance
industry, litigation support, risk analysis, and quality assurance
consulting. The quality assurance department of PIE provides
design development consultation, professional training seminars,
plan and specification reviews, QA observations services, and
building performance testing (water penetration and air
infiltration). Eric and Brian can be reached at 303-552-0177 or by
e-mail at eamhaus@callpie.com or berickson@callpie.com.
Article-Air Barrier
Performance Testing